Town of Windermere continues road work

Several road projects are underway, potentially causing road closures from Monday, March 2, through Friday, March 6.


Stock Photo
  • Southwest Orange
  • News
  • Share

As the town of Windermere continues to work on various road projects, there is expected to be road closures from Monday, March 2, through Friday, March 6. 

Crews are continuing to work on swales and lay sod along Butler and Forest streets and Seventh Avenue. This could cause daytime road closures on Butler Street between Sixth and Seventh avenues as well as on Seventh Avenue between "dirt" Main Street and Butler Street. 

The installation of a concrete curb will take place on Bessie Street and Eighth Avenue. 

Grading of roads and installation of new shell road material on Eighth Avenue between Main Street and East Boulevard, East Boulevard from Ninth and Eighth avenues, and Oakdale Street between Eighth and 10th avenues also will be taking place. 

To allow for this project, Eighth Avenue between East Boulevard and Bessie Street as well as Bessie Street between Seven and Eighth avenues will be closed.

Crews are moving down Second Avenue, working to grade lime rock to prepare for paving from 727 to 806 W. Second Ave.

Also on Second Avenue, crews will be installing lime rock base material for curbs as well as forming and pouring concrete curbs from 914 to 1141 W. Second Ave. 

From 1141 to 914 W. Second Ave., crews will be installing a lime rock base to prepare for paving. 

 