Ocoee is set to begin work on several roadways, including Bluford and Orlando avenues, and Maguire, Tomyn, Marshall Farms and Story roads.
The roadwork is part of the city’s Capital Improvements Street Resurfacing Program. Milling and resurfacing will take place during September and October with most of the work being done at night. Single-lane closures are anticipated, but city officials do not plan on adding any detours.
The first project, which was just completed, began with Geneva Street from Maguire Road to Bluford Avenue, and construction on Story Road from Maguire to State Road 429 began Sept. 6.
The city is working with Orlando Paving Company for all the projects with the exception of Bluford Avenue Phase 2 project, which will be completed by Oelrich Construction Inc., said Ocoee City Engineer Richard Campanale.
The timeline for the projects, which are tentative based on weather conditions, are as follows:
Campanale said the city also is working with Orange County on a joint agreement for the design and construction of left-turn lanes at the Fullers Cross and Ocoee- Apopka Road intersection, and road surveys are currently taking place for the roadwork pertaining to the downtown Ocoee revitalization project.
“Concerning the downtown master plan, roads are being surveyed and 30% design plan phases are being reviewed,” he said. “Oak- land (Avenue Reconstruction) will be the first project to move forward. (We’re) having construction start as soon as the fall of 2019, (because) there is no right-of-way acquisition required.”