Road work continues in downtown Windermere

Several roads will have work done from Monday, May 4, through Friday, May 8.


Courtesy photo
  • Southwest Orange
  • News
  • Share

The town of Windermere is asking people to allow for extra drive time and to be patient as road work continues on several roads in downtown Windermere from Monday, May 4, through Friday, April 8.

On West Second Avenue, crews will continue repairing concrete and paver driveways and grading dirt behind the curb where needed. Crews also will be sodding, mulching or installing gravel. 

Cleanup at Palmer Park also will continue this week, and a crew might be doing limited work in Fernwood Park, such as grading a swale and planting the rain garden/pond.

On Third Avenue, crews might be digging swales this week and grading the road. 

On Bessie Street, East Boulevard and Eighth and Ninth avenues. crews will be performing miscellaneous activities at various locations, which might include right-of-way grading and pouring concrete structures located on East Boulevard. 

On Butler Street and Seventh Avenue, a crew might be doing limited work along Butler and Forest streets as well as Seventh Avenue. 

 

author

Liz Ramos

Managing Editor Liz Ramos previously covered education and community for the East County Observer. Before moving to Florida, Liz was an education reporter for the Lynchburg News & Advance in Virginia for two years after graduating from the Missouri School of Journalism.