If you plan to shop at the Winter Garden Village at Fowler Groves this week and next, you can expect some detours. DDR Corp. is closing sections of the parking lot to do some scheduled maintenance work on the asphalt.
Recoating work will take place during the night and requires 24 hours for it to cure.
The following schedule will be followed:
Section 1 – Monday, July 10 – the northernmost entrance at the light
Section 2 – Tuesday, July 11 – the eastbound strip in front of stores including Bath & Body Works and New York & Co.
Section 3 – Wednesday, July 12 – the eastbound section just east of the gazebo
Section 4 – Thursday, July 13 – the westbound section just east of the gazebo
Section 5 – Monday, July 17 - the westbound strip in front of stores including Carter’s and American Eagle Outfitters
Section 6 – Tuesday, July 18 – the northernmost exit at the light.
Rain dates are Wednesday, July 19, and Thursday, July 20. Any section unable to be completed on the scheduled day will be done on these days.
The Winter Garden Village is at 3251 Daniels Road, Winter Garden.